Shuliavsky bridge in Kyiv closed from today

The construction of the new overpass will have been finished by the end of this year
09:17, 16 March 2019

The disassemble of Shuliavsky bridge in Kyiv
kiev.informator.ua

Shuliavsky overpass is closed due to dismantlement works today. Besides, it is expected that the reconstruction of the overpass will be completed the same year. The Trasport Infrastructure Department of the Kyiv City State Administration reported this.

The dismantlement works will begin tomorrow, March 17.

Related: Ukraine ready to fix demolished bridge in Stanytsia Luhanska, - Marchuk

“The first stage should be dismantling of the contact network, the support columns, the cornice blocks, the sidewalk consoles, the asphalt concrete coating, the beams of runways and partial dismantling of the grilles”, - Olexandr Zdolnyk, the main engineer of the Trasport Infrastructure Department of the Kyiv City State Administration stated.

The construction of the overpass with a length of 158.17 m, bike paths (length - 741 m), left and right convergence congresses, reconstruction of the underground pedestrian crossing, and landscaping is planned to be finished by the end of 2019.

Related: Bridge collapses in Kyiv near Darnytsia metro station, - photo

Earlier, the start of the reconstruction of the bridge was anticipated in May 2018. However, the works have been postponed for an indefinite period. The reason was a petition with an alternative version of the reconstruction, which the City Council was obliged to consider. The Kyiv City State Administration determined the final version of the reconstruction of the interchange at Shuliavska last year in May, the cost of the works is expected to be USD 14,5 million. 

Related: Collapse of bridge in Kyiv